Do the times in labour and materials files (SMVs) include travel time?
No. The times in the labour and materials files are for completing the job once on site. Travel times should be added in "padding". Travel and other non-productive time should be taken into account by the contractor when calculating the % upliftBack to contractor's frequently asked questions